Introduction
First Phase Development of Kwu Tung North and Fanling North New Development Area
The government has completed the statutory planning procedures for amendment of the Outline Zoning Plan (OZP). The statutory OZPs for the KTN and FLN NDAs were approved by Chief Executive on 16 June 2015. The plans and schemes of the proposed roadworks and sewerage works under PWP Item Nos. 7747CL and 7759CL were gazetted in December 2015. The amendments to the proposed roadworks and sewerage works were also gazetted in November 2016. The Chief Executive in Council had authorised the works and the notice was gazetted on 14 December 2018. All affected private land reverted to the government in late 2019. The land clearance was completed in 2023 according to the project implementation programme. Site formation works is in progress.
Remaining Phase Development of Kwu Tung North and Fanling North New Development Area
The plan and scheme of the proposed roadworks and sewerage works under PWP Item No. 7828CL was gazetted on 30 September 2022. The Chief Executive in Council had authorised the works and the notice was gazetted on 29 December 2023. The affected private land reverted to the government in April 2024. The government land clearance is according to the project implementation programme.